Bath Road, Brislington

Bath Road, Brislington

Category

Location

Bath Road, Brislington

Contract Period

7 weeks

The former John Peer factory on Bath Road in Brislington, Bristol, has been a longstanding derelict site, attracting issues such as vandalism and graffiti, fly-tipping and anti-social behaviour. The site was recently acquired with the aim of redeveloping the site into affordable housing. Weaver Demolition commenced demolition of the abandoned factory towards the end of 2024 and the project took 7 weeks to complete.

Project Overview

The demolition of the former factory was a significant undertaking aimed at clearing the site for the future development of new housing.

 

The demolition process involved several key steps:

 

  • Site Preparation: Prior to demolition, preparatory works were initiated, which included securing the site, conducting necessary surveys and managing on-site ecological issues.
  • Structural Demolition: The main demolition phase involved the careful dismantling of the factory structure. Given the building’s size and proximity to other properties, this required meticulous planning to ensure safety and to minimise disruption to the surrounding area.
  • Debris Clearance: Following the demolition, the site was cleared to prepare the land for subsequent development and to address any environmental concerns associated with the remnants of the old structure.

 

 

Project Requirements

  • Management of ecological issues
  • Asbestos removal
  • Total demolition of old factory building
  • Removal of hard standings
  • Segregation of different waste streams for recycling
  • Crushing and screening of aggregates
  • Backfilling

 

 

 

 

Environmental Impact

Careful consideration was given to minimising environmental impact and disruption to the local community. Key measures included:

 

  • Recycling of materials on site – Weaver Demolition specialises in on-site demolition, ensuring as much material as possible is crushed on site and re-used on site, thereby reducing waste send to landfill.

 

  • Adherence to environmental standards – Weaver Demolition’s ISO:4001 Environmental Management certification reflects our commitment to best practices in environmental and waste management standards

 

 

Key Benefits to the Client

  • Enhanced community relations – by addressing the longstanding issues associated with the derelict site and strengthening community support for future redevelopment
  • Site preparation ready for redevelopment – facilitating a fresh start for the project
  • Meeting sustainability goals – by engaging a contractor specialising in recycling, the client was able to ensure all materials were processed sustainably

 

Project Summary

The completion of these demolition activities has rendered the site ready for redevelopment, with plans underway to construct new housing that aligns with the community’s needs and the area’s urban landscape.

 

 