Hartcliffe Way, Bristol

Hartcliffe Way, Pedestrian Bridge

Category

Location

Hartcliffe Way, Bristol

Contract Period

3 Days

A redundant pedestrian footbridge spanning a main city dual carriageway was removed throughout the course of two nights within restricted road closure hours.

A full lift plan was developed in line with the demolition method statement to ensure the smooth dismantling and removal of the bridge. Weaver Demolition’s in-house fleet of HGV’s and specialist trailers provided the perfect transport solution for the movement of bridge sections to our nearby yard for final dis-assembly.
Works were completed safely and to the client’s satisfaction, with the road re-opening 5 hours ahead of programme.