Engines, pumps and tanks were drained, disconnected and lifted out, followed by the demolition of the various structures. All associated pipework to the perimeter lagoon was also removed. Basements were infilled and compacted in layers with selected site won material to leave the area in a safe and tidy condition. Various items including 2nr generators were transported to a near-by site for future re-use.