In summary, works comprised of the site clearance, licensed and non-licensed asbestos removal, followed by high-reach and standard mechanical demolition of multiple structures situated within the site to make way for a new commercial and residential development.
Due to the positioning of the site, consideration had to be given to the neighbouring properties which consisted of the SS Great Britain, Albion Dry Dock as well as a number of Commercial and Residential Properties. Strict adherence to the projects party wall agreements was fundamental to the successful completion of the project.
As with every project, a full and bespoke set of Risk Assessment and Method Statements (RAMS) were developed in line with site specific and programme requirements to ensure the safe and timely delivery of the project. This large scale project was delivered on time over a period of 21 weeks,
Before work commenced, a number of items were identified by the client that had to be carefully salvaged and stored so that they could be incorporated into the future development of the site.All arisings were segregated prior to leaving site and brick and concrete arisings were crushed to 6F2 specification on site and stockpiled for future reuse.
©2019 – Weavers Demolition | All right reserved
Fill in the form below with your requirements and your contact details and we will get in touch with you as soon as possible.